Good Afternoon,
Your 2022 CCR has been completed and is available for viewing. Any Questions in regard to the CCR need to be directed to info@nwwatersystems.com
The Silver Hawk Water Treatment pilot study is currently under review.
Silver Hawk Treatment Design
Below is what has been completed as of today (12/6/2022):
DOH completes review and requires follow up questions Completed, May 2022
Engineer responds to questions, Completed July 2022
DOH approved Pilot Study - Completed in August 2022
Final Treatment Design submitted to DOH for review/approval - Completed, December 2022
Below is a tentative timeline as of today (12/6/2022):
February 2023 - DOH completes review and requires follow up questions
March 2023 - Engineer responds to questions
April 2023 - DOH approves Treatment Design and construction can begin
|